BIPV Integrated Design: Why a Roof Should Be Designed Once, Not Twice
News

BIPV Integrated Design: Why a Roof Should Be Designed Once, Not Twice

2026-11-25
Table of Contents Hide

Most rework in BIPV projects is not caused by defective PV modules. It happens because two sets of drawings do not match.

The structural roof drawings and the solar PV layout drawings may each pass their respective reviews. But when combined, they can conflict over loads, access walkways, openings, and waterproofing. The rework then takes place on site.

This article explains where the design interfaces break down, how much these issues can cost, and why both disciplines must be coordinated by the same design team from the preliminary design stage.

For project-specific roof load calculations and PV module layout design, simply provide your roof area, project location, and planned installed capacity.

Email: info@xzbesta.com

 

 

One Roof, Two Sets of Drawings: Where Do the Design Interfaces Break Down?

The Structural Engineer Sees the Roof as a Structural Component

In structural drawings, the roof consists of profiled steel sheets and purlins. The load transfer path runs from the roof sheets to the purlins, then to the rigid frames and finally to the foundations. The load path is clear, and each component has its own structural calculations.

Structural engineers focus on dead loads, live loads, snow loads, wind loads, and the number of openings in the roof.

 

The Solar PV Engineer Sees the Roof as an Installation Interface

In solar PV drawings, the roof is covered with hundreds of PV modules, mounting structures, clamps, cable trays, maintenance walkways, and inverters. The drawings need to address module layout, series and parallel connections, shading, and cable losses, with a focus on how much PV capacity can be installed per square meter.

Although the two sets of drawings may use the same terminology, they do not necessarily refer to the same physical components or design requirements. A BIPV roof system is an integrated photovoltaic building product. It serves as both a waterproof roofing layer and a power-generating layer. Defining it from only one discipline will inevitably leave half of the requirements unaddressed.

 

 

Three Consequences of Design Interface Mismatches

Loads: Wind Uplift Is the Real Risk, Not the Weight of the PV Modules

The dead load of PV modules and mounting structures is typically calculated at 15–25 kg/m², and most projects make allowances for it. What is more likely to be overlooked is wind uplift.

Under negative wind pressure, the roof is subjected to upward suction forces, acting in the opposite direction to dead loads. This changes the stress conditions of the roof sheets, connectors, and purlins. According to the applicable load codes, wind loads must be calculated separately for different roof zones. The design values at corners and edges are significantly higher than those in the central zone, yet PV arrays often extend right into these corner areas.

Retrofitting existing roofs is particularly challenging. The original structure may have been designed only to support the building envelope, with limited reserve capacity. Once PV module dead loads and wind uplift forces are added, the existing structure may no longer have sufficient capacity.

 

Access Walkways: Without Proper Roof Access, Maintenance Personnel May Step on PV Modules

PV modules need regular cleaning, inspection, and individual module replacement. Three questions must be addressed in the drawings: How do maintenance personnel access the roof? Which routes should they follow? Where are they allowed to step?

If these details are not specified, workers will simply take the most convenient route on site. Foot traffic can cause microcracks in PV cells that are invisible from the outside but affect power generation. The resulting loss in output may not become apparent until several years later.

 

Waterproofing and Responsibility: Three Areas Are Particularly Prone to Water Leakage

Three locations are especially vulnerable to water leakage: mounting support penetration points, gutters, and expansion joints.

When two separate suppliers are responsible for the project, the structural contractor may claim that the roof is the solar PV supplier’s responsibility, while the PV supplier may argue that the supporting structure belongs to the structural contractor. This makes responsibility difficult to determine.

An integrated roofing system uses structural waterproofing details rather than relying on sealant alone. Its waterproofing performance depends on the structural details and roof slope. Further information is available in our Structural Waterproofing System.

 

Table 1. Common BIPV Design Interface Mismatches and Their Solutions

Type of Design Mismatch On-Site Problem Potential Cost or Consequence How Integrated Design Prevents It
Insufficient load allowance Installation is stopped halfway because the existing purlins do not have sufficient load-bearing capacity, requiring additional reinforcement 15%–25% of the additional installation budget, including production downtime and roof dismantling and reinstallation Calculate dead loads and wind uplift together at the preliminary design stage
No maintenance access walkways Maintenance personnel step on PV modules, causing microcracks Gradual reduction in power generation and high replacement costs Include maintenance walkways and roof access points in the PV layout drawings
Conflicts between roof openings and expansion joints PV arrays extend across expansion joints, causing shear forces on mounting supports Rework and redesign of the PV layout, resulting in project delays Use one shared roof reference drawing for both structural and PV design
No allocated space for inverters Inverters are mounted on walls temporarily during installation, resulting in longer cable routes Increased cable losses and damage to the building facade’s appearance Determine equipment locations and cable tray routes during the preliminary design stage
Unclear waterproofing responsibilities Both parties shift responsibility to each other after water leakage occurs Lengthy claims procedures, with the owner potentially bearing the costs Establish a single responsible party and adopt structural waterproofing details

 

 

Coordination Starts at the Preliminary Design Stage: Five Key Decisions

If these five decisions are made too late, they can lead to rework throughout the subsequent project stages.

 

What Each of the Five Decisions Determines

Roof panel profile determines how the mounting system is connected. Standing seam roofs use clamps, while profiled steel sheet roofs use through-fastened or specially designed connectors. BIPV systems use an integrated component-based design in which the PV system and roof panel are designed as one system.

Purlin spacing determines the PV module layout. Whether modules are supported along their long sides or short sides also affects the required purlin spacing. For further details, see our Guide to Purlin Spacing and PV Module Support Design.

The locations of expansion joints, gutters, and roof openings determine where PV arrays need to be divided.

Parapet height determines potential shading and wind pressure zones.

Equipment locations and cable tray routes determine where concentrated loads will occur.

 

Who Takes the Lead, and What Happens If Decisions Are Delayed?

Three decisions are led by the structural discipline, while two require joint confirmation. If the responsible parties are not clearly defined, each team may assume that the other has already made the decision.

 

Table 2. Design Responsibilities and Consequences of Delayed Decisions

Key Design Decision Responsible Discipline(s) Consequences of Delayed Decisions
Roof panel profile Structural engineering The mounting system may not be compatible, requiring changes to the roof panel profile or mounting system
Purlin spacing Structural engineering + Solar PV engineering The PV module layout must be redesigned, potentially reducing power generation
Expansion joints and roof openings Structural engineering + Solar PV engineering PV arrays may cross expansion joints, causing shear forces on mounting supports
Parapet height Architectural design + Solar PV engineering Shading may cause mismatches in series and parallel PV connections
Equipment locations and cable trays Solar PV engineering + Construction Decisions are made temporarily on site, resulting in increased cable losses and damage to the building facade

 

 

How Integrated Load Calculations Are Performed

Load Combinations Must Include Requirements from Both Disciplines

Dead loads include PV modules, mounting structures, clamps, cable trays, cable trunking, and inverters. Live loads are determined based on maintenance requirements, snow loads are based on the project location, and wind loads must account for both positive and negative pressure.

All four types of loads must be considered in the same load combination to determine the actual internal forces in the purlins and rigid frames. Calculating them separately and simply adding the results may overlook the applicable load combination factors.

 

Both Disciplines Must Use the Same Design Boundary Conditions

The roof elevations, slopes, wind pressure zones, and opening locations in the structural calculation report must be fully consistent with those in the solar PV layout drawings.

If two separate teams prepare the drawings independently, even if each team reviews its own work, a 200 mm difference in elevation or a relocated roof opening can invalidate the structural calculations.

The IEA PVPS BIPV Task Force identifies this as one of the industry’s major barriers in its Task Description. It emphasizes the need for design processes that enable effective coordination among architects, engineers, and material specialists, rather than allowing each discipline to complete its work independently.

The load values themselves should be determined in accordance with the applicable standards, including the EN 1991 series under the European Eurocodes framework.

 

 

How to Implement Integrated Design in Practice

One Joint Drawing Review Instead of Two Separate Handover Processes

A practical approach is to bring together the structural, solar PV, and construction teams to review the same roof drawing and confirm the five key design decisions, rather than having each discipline focus only on the completeness of its own drawings.

The output of this review should be one coordinated drawing that combines the structural layout, PV module arrangement, maintenance walkways, roof openings, and equipment locations on the same reference drawing. All subsequent disciplines should use this drawing as the common design basis.

 

In-House Design Capabilities Ensure Clear Responsibility

ZM-Besta has its own design institute, where structural and solar PV drawings are prepared within the same organization, using one coordinated set of roof drawings.

Our design work uses PKPM, 3D3S, MIDAS, and STAAD.Pro. We hold a Class A Specialized Design Qualification for Light Steel Structures and can prepare designs in accordance with European and American standards, as well as provide engineering design consultancy.

For new-build projects, see our Guide to Integrated Steel Structure and BIPV Design. For existing factory roof renovation projects, see our Integrated Roof Replacement and Steel Structure Solution.

For projects requiring engineering design coordination and structural calculation reports, please submit your project requirements through our Steel Structure Engineering Services page.

 

 

Frequently Asked Questions

Q1: Can BIPV be installed directly on an existing steel structure factory building?

A structural assessment must be carried out first. The original design may have considered only the building envelope, and the available load-bearing reserve may not be sufficient. The load-bearing capacity of the purlins, connections, roof slope, and drainage system must all be checked. If the existing structure does not have sufficient capacity, reinforcement must be completed before installation.

 

Q2: Can structural and solar PV design still be coordinated if they are handled by two different suppliers?

Yes, but the design interfaces must be clearly documented. Four items must be included in the contract appendices: the roof reference drawing, load design boundaries, locations of roof openings and mounting supports, and waterproofing responsibilities. Verbal coordination alone will inevitably fail by the construction stage.

 

Q3: Do BIPV loads affect the selection of the factory building span?

Yes. The dead loads of PV modules and mounting structures must be included in the rigid frame calculations. The greater the span, the more significant their impact may be. For integrated projects, PV loads must be considered from the initial span selection stage.

 

Q4: Does integrated design take longer than designing the structural and solar PV systems separately?

The preliminary design stage may take slightly longer, but the overall project duration is usually shorter. The additional time spent during the design stage can prevent structural reinforcement, rework, and production downtime during construction. Rework often affects activities on the project’s critical path.

 

 